Triton College begins third phase of pavement replacement; driving entrances to close temporarily

Triton College is nearing the start of the third phase of a multi-year asphalt pavement replacement project on the west campus. This phase will be broken up into three parts and includes the re-pavement of Lot 2, Lot 3, Lot 4, and a section of Hemingway Drive  (see map).

AsphaltPavementProjectPART 1Thursday, May 21, 2015 – Friday, July 24, 2015

Parking Access.  There will be NO access to Lot 3 and Lot 4 during this part of the project. There will also be NO access to Hemingway Drive between Lot 2 & 3 and Lot 4.  Vehicles will not be able to access the North lots from the South or the South Lots from the North during this period.

Access to the O Building (Operations & Maintenance), and the P Building (Human Resources, Payroll, Marketing, and Creative Services) will be possible by sidewalk. O & P Visitors will have to park in Lot 5

PART 2Monday, July 27, 2015 – Monday, Sept. 14, 2015

Parking Access.  There will be NO access to North Section of Parking Lot 2 during this part of the project.

PART 3Tuesday, Sept. 15, 2015 – Friday, Oct. 30, 2015

Parking Access.  There will be NO access to South Section of Parking Lot 2 during this part of the project.

We appreciate your patience as we continue to enhance our campus for the safety of our students and the Triton College community.

Click here for more information about Triton’s Pavement Replacement Project.

Advertisements
This entry was posted in Pavement Replacement Project and tagged , , , , , , , . Bookmark the permalink.

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s